Manufacturing — Plant Calendar & Capacity Assumption Registry

S&OP and AI forecasts should share one approved plant calendar and capacity assumption set—including shutdowns.

Why this is needed

  • Plans ignore known shutdowns stored in someone's spreadsheet.
  • Capacity assumptions differ by planner.
  • Fabric planning models need warehouse-native calendars.

Proposed entities in EntiHub

Governance settings

Setting Recommended value Why
approvalRequired true Calendar/capacity changes affect all plans.
historyEnabled true History of assumption versions.
allowSameAuthorApproval false Maker/checker separation for sensitive changes.
deletedRetentionDays 90 (or higher) Soft-delete retention for auditability.

Entity definition (YAML sketch)

name: plant_calendar
displayName: Plant calendar
domain: Manufacturing
description: Plant calendar
version: "1.0.0"
approvalRequired: true
historyEnabled: true
deletedRetentionDays: 90
displayRefColumn: calendar_code
uniqueConstraints:
  - name: uq_plant_calendar_0
    columns: [calendar_code, calendar_date]
columns:
  - name: calendar_code
    dataType: string
    nullable: false
    maxLength: 64
  - name: plant_code
    dataType: string
    nullable: false
    maxLength: 32
  - name: day_type
    dataType: string
    nullable: false
    maxLength: 32
  - name: calendar_date
    dataType: date
    nullable: false
  - name: capacity_units
    dataType: decimal
    nullable: true
  - name: status
    dataType: string
    nullable: false
    maxLength: 16

YAML sketches

Sketches highlight the important fields and governance flags. Trim or extend columns to match your domain. See Setup Entity for the full YAML reference.

Sample data

calendar_code plant_code day_type calendar_date capacity_units status
CAL-SK1-2026 SK1 working 2026-09-28 1000 active
CAL-SK1-2026 SK1 shutdown 2026-12-24 0 active

Benefits for the company

  • Shared calendar for S&OP and AI forecast.
  • Shutdowns are first-class data.
  • Versionable capacity assumptions.